Client: Chemical Company
10.12.2024
Background
A global leader in coating systems, sought to optimize its distribution network across North America and EMEA. Facing high logistics costs and complexity due to multiple distribution centers, Client's network included 41 active sites in EMEA and 29 in North America, serving distinct business units in Industrial, Mobility, and Refinish. The company aimed to reduce these costs while maintaining or improving service levels.
Objectives
1) Streamline the distribution network to reduce operational expenses
2) Maintain service levels for different business units, with lead times of 1–3 days for the respective BUs
3) Enhance sustainability through reduced CO₂ emissions and improved handling processes
4) Minimize redundancies and eliminate costly or underutilized sites
Challenges
The client faced strict regional regulations, high warehousing costs, and the need to balance logistics between 3PL and owned sites. Specific challenges included:
Approach & Methodology
Miebach Consulting conducted a comprehensive analysis,
which included:
1. Data Validation and Baseline Assessment
Site visits, data visualization with Power BI, and mapping current network flows for accurate cost and service analysis.
2. Scenario Development: Three primary scenarios were proposed
Scenario 1: Reduction of sites with clusters, using one main hub per region.
Scenario 2: Enhanced lead times with 1- to 3-day delivery options.
Scenario 3: A single hub for all European distribution (excluding the UK and Turkey).
3. Optimization Models
The team applied advanced modeling for each scenario to assess factors such as transportation costs, warehousing costs, working capital, and service levels. These models also included sensitivities to handle fluctuations in growth and logistics costs.
Implemented Solution
Based on scenario analyses, a cluster-based approach with regionally optimized hubs was recommended. The final solution included:
Warehouse Reduction: Targeted reduction from 41 to a minimum of 30 sites in EMEA.
Site-Specific Adjustments: Specific site strategies, such as consolidating Italian warehouses, shifting some functions within the UK and Ireland to a single large facility, and assessing logistics options in EMEA.
Transportation and Inventory Management: Improvements in fill rates and outbound processes, along with frequency adjustments for cost efficiency. |
Result & Benefits
Network optimization indicated 12% annual savings with possible additional 4% from reduced delivery frequency
1. Cost Savings: An estimated $16.1 million in annual savings ($11.5M through Network optimization)
2. Service Enhancements
3. Environmental and Financial Gains
+ Long-Term Viability
Miebach’s optimized network offers the client a robust foundation for future growth, allowing flexibility to adapt to changing business conditions and regional demands without compromising service levels.